Work Continues on Chernobyl Shelter

According to the Chernobyl Atomic Energy Station's Information Department, by April 25, 2008, 80% of the load carried by beams B1 and B2 in the original Sarcophagus will be transferred to newer external supports. Repairs to the structure's roof are expected to be completed this summer.

Following the completion of the above work, preparations for the physical construction of the base for the New Safe Confinement can begin. Chernobyl Plant Director Igor Gramotkin hopes that work connected with the New Safe Confinement will not only go according to plan, but even proceed ahead of schedule.

The current plan is for physical construction of the New Safe Confinement to begin in April 2009.