Chernobyl NPP to be Eliminated by 2065
Ukraine’s Verkhovna Rada has approved a program for the complete decommissioning and elimination of the Chernobyl Nuclear Power Plant by 2065. The work will be completed in several phases:- 2010-2013: Nuclear fuel will be removed from all reactors and temporary storage and moved to long-term storage
- 2013-2022: Preserve reactor facilities
- 2022-2045: Experts to reduce radioactivity of the reactors
- 2045-2065: Dismantle the facility